From August 10 until September 27
- faced some of the kitchen cabinets with cypress
- built a corner kitchen cabinet on the left side of the sink then rebuilt it
- built the matching cabinet on the right side of the sink
- changed the fittings on the stove
- primed, caulked, and puttied
- put up beam above sink between kitchen cabinets and installed hanging mason jar lights and put up a beam in the dining room and installed the light fixture
- rented a man life again and painted the remainder of the house with 2 coats and installed the flashing
- put down a piece of linoleum flooring in upstairs bathroom
- called in reinforcements to run plumbing from water heater upstairs to bathroom upstairs and to the downstairs master bath and connect the upstairs AC drainpipe to the new plumbing and install the upstairs shower plus rough out the plumbing for the toilet and sink
- built an access door for new plumbing that is connected to master bath through wall in dining room
- put in bead board plywood for the walls in the upstairs bathroom
- installed Sara's floor
- put in Allie's ceiling which is rusted tin that has been sealed
- finished running and tying in electrical lines
- put in bead board plywood ceiling in master bedroom
- put up beam in master bedroom
- put up door and window facings
- put in floor and ceiling molding in master bedroom
- put in one section of missing wall in office/classroom using salvaged pine tongue and groove and did more demo on a remaining piece of wall to prepare the wall for closing in with the salvaged wood
- installed another sub panel for electrical lines
- connected stove and outlets on the island, connected upstairs water heater
- put in insulation and bead board plywood in about 1/2 of the remaining wall in office/classroom







It's coming along so well!!! Love and miss you guys!